|

|

|
How Would You Do It?
Visitors to this web site sent in their obelisk-raising
theories during the Online Adventure in March 1999; selected
theories and responses from the expedition members are posted
below. If you'd like to review the ideas that were previously
suggested during a live question-and-answer event with
archaeologist Mark Lehner on May 19, 1998, go to
An Archaeologist's Perspective.
Theory:
If I were given the job and the resources to do it, what
better way than to use water?
-
They obviously had the shipbuilding technology to
transport such items, so they could reverse this
procedure and build a dry dock at the site.
-
Provide the monolith with flotation collars at optional
locations. The collar should be located at just
overcenter (lengthwise) and the secondary flotation
collar located toward the base.
-
Close the container and fill it with water and when the
desired elevation is achieved, flood the base.
Dennis Scott-Jackson Burnaby, British Columbia
Response from Roger Hopkins, stonemason:
Dennis, the Egyptians were really great at building canals
and dams, but they seem to be lacking in putting all the
hydraulics into transferring water from one place to
another. It's doubtful that they would have been filling
chambers with water. To use this flotation idea, they would
have had to have mastered moving great quantities of water,
because no matter what they built it would have leaked quite
rapidly.
Theory:
I read your dispatch about the pulling progress. (See
'Pulling Together'.) If the pullers cannot maintain the dragging, then maybe
the approach is just a few feet at a time. Try anchoring the
ends of the ropes, then attach ropes to the middle and pull
perpendicular. You increase your mechanical advantage. Your
advantage finally drops to just 2X when the ropes hit 30
degrees from the direction you are trying to pull (at 10
degrees it's more than a 5X advantage, 20 degrees it's
3X—try the math).
Andrew Kulich Rochester, Minnesota
Response from Roger Hopkins, stonemason:
Andrew, I agree with you that there is a lot of mechanical
advantages to pulling rope perpendicular, but in my own
personal opinion, I believe that they only pulled the
obelisks very short distances. They would bring the obelisk
by boat as close as possible and then they would have
probably used rollers and a very firm rope—a
combination of rollers and levers and
rope—pulling—because it's a little easier to
control. If you're depending entirely on ropes, they can act
unfavorably at times.
Theory:
After carefully observing the obelisk, it seems as if it was
carved after being raised. It is very possibly easier to
raise the obelisk in an "un-careful" state (not wanting to
damage the carving) using a vertical drop. Being pulled
carefully by rope over the drop (as seen in many Egyptian
demonstrations), the obelisk would be pulled and standing at
a vertical state.
(name witheld by request)
Response from Roger Hopkins, stonemason:
It's always best when you're carving into a block of granite
to be working on the flat. So, it's probably likely that
they did the carvings and rotated it on the ground. On the
vertical, you could do some changes there, but it requires a
lot of staging and it's more difficult work when the granite
is in a standing position. As for being careful, they would
had to have been careful whether it was carved or uncarved,
because they went to a lot of trouble to get that block of
stone there.
Theory:
You almost had it the first time. Why couldn't you raise it
with oxen? I would suggest the A-frame to be tilted more
towards the pulling team from the start or set up two
shorter A-frames in a series.
(name witheld by request)
Response from Henry Woodlock, Whitby Bird & Partners:
You are right. When the rest of the team did their first
attempt, A-frames in series would have helped. However, when
you consider the largest obelisks, the use of A-frames
becomes less appealing. The forces involved require enormous
frames. The key to using this technique is getting elevation
height above the object and reducing the force required by
tilting the obelisk to a steep angle first.
Theory:
As far as I could tell from your program, the problem is
essentially one of controlled descent. Two methods were
used, and a combination of the two seems to be reasonable: A
very steep ramp (steeper than that used in the program),
with raised blocks built into the ramp that guide the sled
in its descent. These blocks could even be placed at an
angle or shaped for the purpose of catching and guiding the
sled. It would seem that these blocks, or even the whole
ramp structure, could be reused, so it's conceivable that
most of the work that you would have to do in raising an
obelisk would be a matter of fabricating stonework that the
Egyptians had on hand from past projects.
Markers would have to be placed at the runway at the top of
the ramp to guide the sled; the blocks that physically guide
the sled will, of course, be buried in the sand used to
control the descent of the sled. The sled would be pulled
onto the bed of sand to the point of balance, the sand would
be released, and the sled would slowly slide down the (very
steep) ramp. The descent is controlled by a combination of
sand removal and support ropes from behind. The bottom of
the obelisk could be fitted into the turning groove in this
manner. The sled runners, the height of the block, the
location of the turning groove, and the base of the obelisk
would have to all be coordinated, but this should not
require any great feat of math (not that I pretend to be an
expert in either math or the ancient Egyptians' grasp of
it).
Anyway, setting the base of the obelisk, I believe, is a
matter of a sand-controlled, block-guided descent down a
very steep ramp to a pre-measured destination. The steeper
the ramp, the better (I would guess), because this would put
the obelisk at such an angle so that getting it upright
would be easier.
Once this was done, many possibilities present themselves. A
long structure could be built at a right angle from the top
of the obelisk before it is erected: It would look like an
inverted "L." The beam perpendicular to the obelisk would
have to be supported from the end of the beam farthest from
the obelisk to the base of the obelisk, creating a
triangular structure laying against the side of the obelisk
and attached to it; the widest part of the triangle at the
top of the obelisk and a pointy end at the bottom. (The
obelisk itself would form one of the longest sides of the
triangle, with its base at the most acute angle of the
triangle at the base of the obelisk.) I don't know if the
Egyptians from that period understood the idea that a
triangular brace will make a structure stronger, or if they
had material which would make such a structure possible.
Assuming that such a structure is feasible, it would be
attached to the obelisk before it was lowered into the pit.
The obelisk would be lowered as before, and the sandpit
would be disassembled around the obelisk and its attached
structure once the sand was drained. Many ropes would be
attached to the end of the beam perpendicular to the top of
the obelisk on the end of the beam farthest from the
obelisk.
Someone would then have to climb out onto the end of the
beam and start hoisting up sandbags. As a practical touch, a
little seat could be built onto the end of the beam for this
purpose. This would add comfort and efficiency, because I
contemplate a slow pace in this phase—about 10 to 20
pounds at a time. Since we are talking about such huge
weights, this would take a good deal of time, but by the
same reasoning, a platform with three men could work pretty
steadily at the end of the beam.
This method would, of course, present the problem of
enormous torsion at the base of the obelisk if the
counterweight were not balanced along the midline of the
obelisk. Also, if the whole contraption were not balanced
properly, the structure would likely collapse; it is not
built to take lateral strain in one direction. Lateral
strain in two directions, however, would have the net effect
of balancing the whole contraption. The balancing could be
done in the following manner. Ropes would be placed like guy
wires on each side if the obelisk and structure. These would
be "paired" ropes, two ropes to each support. The ropes
could then be twisted with large poles to control the
lateral movement of the obelisk and the counterweight.
Further, the ropes could be stretched over A-frames to make
them more manageable. Someone could "eyeball" the structure
from a distance, and with either runners or hand signals,
fine-tune the raising of the obelisk.
The whole would, of course, have to be supported from behind
in order to keep it from toppling forward once the
counterweight went past the point of balance. These support
ropes would be pre-twisted in a manner that the tension on
them could be slowly released. Once the obelisk was upright,
the sandbags would be cut away one by one, and the tension
on the ropes slowly released, and the obelisk would be left
standing once the structure was cut away from it.
A theoretically similar method to the above involves the use
of A-frames. Instead of one A-frame, however, an array of
A-frames would be used, much in the same manner as a very
large team of horses is arrayed from a very heavy load. Some
of the A-frames would be closer to the "load" and some would
be farther away, but in the end, all would pull in the same
purpose. Again, lateral guide ropes would be twisted to
control lateral movement, and sandbags would be used to pull
the A-frames.
I really think this would work. The ropes could be attached
to the obelisk and then stretched over the A-frames.
Sandbags could then be attached to the ends of the ropes
after they are stretched over the A-frames. Again, the
sandbags would be attached one at a time. A few bags could
be attached in the beginning to make the A-frames stand up,
and then two people could be stationed at each frame to
hoist sand bags. Note that this would not require cruelly
heavy labor on the part of anyone, and the methods used
would be only moderately dangerous. Further, it would not
require huge crews, and could be accomplished with about a
hundred people (assuming that each frame can pull a ton).
The A-frames could probably not lift the whole obelisk at
once, and would have to be moved several times in order to
bring it all of the way up. The obelisk, of course, would
have to be supported from behind each time it was lifted a
little. This would probably change their relative positions,
and they would have to be initially spaced so that they will
not interfere with each other throughout the whole of the
project. Again, the ascent of the obelisk would be
controlled laterally and from behind with twisted ropes.
Once the obelisk was upright, the sandbags would be slowly
cut away from the A-frames and the tension on the ropes
would be released.
To sum up, I would raise the obelisk by sand-controlled and
block-guided descent down a very steep ramp and then use a
large counterweight balanced by ropes to help in raising the
obelisk. Or, I would use several A-frames to slowly pull the
obelisk into position once it was placed in the turning
groove by the controlled descent described above. Again,
sand, and not brute human pulling power, would be used as
both the force and control needed to raise the extremely
heavy obelisk once it was in the turning groove.
Marcus Vise New Orleans, Louisiana
Response from Henry Woodlock, Whitby Bird & Partners:
The difficulty with the sand method is twofold. First, there
is the size of the construction required to get the height
of the ramp. Sandbanks are naturally at quite a shallow
angle, and if it is banked up high enough for the big
obelisks, the pile would cover an enormous area. I sometimes
feel that the implications of this have not been considered.
In the temples, monuments are closely spaced and all would
be covered in sand during the erection of the latest
obelisk.
The second difficulty with sandpits is control. How do you
let sand out of a chamber evenly to avoid the obelisk going
off course? We saw the difficulties on the last NOVA
program, and that was with a tiny obelisk. A 'sand-box' has
been suggested by some archaeologists. The suggestion has
been that mudbrick was used to enclose the sand. I remain
skeptical about the ability of mudbrick walls to resist the
lateral pressures of the huge height of sand. Sand control
makes sense to me for cuboid heavy objects like a
sarcophagus or some statues, but not for the shape of the
obelisk.
The raising methods you describe are all feasible from a
steep angle. The reason I hesitate to use an A-frame to pull
the obelisk the last few degrees to vertical is the risk of
overturning the obelisk. It may be easier to pull in a less
direct way at the front by 'swigging' (pulling horizontally
on anchored vertical ropes) and brake the obelisk at the
back to achieve fine control.
Theory:
Why don't you use the sled and A-frame idea, but then use
the sled to help push the obelisk up?
(name witheld by request)
Response from Henry Woodlock, Whitby Bird & Partners:
There are two major problems with sliding the obelisk down a
slope on its sled. First, you don't really have control. It
is not so bad on a short obelisk as with the one used in the
first NOVA Obelisk program, but getting the obelisk on line
as it slides is very difficult. Second, pulling the obelisk
up with an A-frame requires tremendous force, because you
are working against the weight of the stone all the time.
Just imagine the number of people required to pull up a
400-ton stone in this manner—you are talking about
thousands of laborers!
Theory:
I would first cut the thing from the bottom, then use a
crane and a lever.
(name witheld by request)
Response from Henry Woodlock, Whitby Bird & Partners:
I'm not sure what you mean by 'cut from the bottom,' but I
presume you mean an ancient crane! In a sense, we will
investigate ancient lifting gear when we try to pull the
butt end of the obelisk down. By combining timber members in
compression and rigging in tension, we have a type of crane
system off the end of the obelisk, giving us additional
leverage to rotate the obelisk.
Theory:
Perhaps they dug canals to the spot where they wanted to put
the stone and brought it there from quarries by the river,
by raft, and then dug a deep hole at the end of the small
canal, and slid the obelisk off the raft and in to the deep
hole while pulling on it with ropes, then filling up the
canal and holding the stone in place until the earth
dried—just a thought.
Austin, TX
Response from Owain Roberts:
Well, rafts are not suitable, because the amount of buoyancy
available on a raft isn't sufficient—even in a big
raft—to float an obelisk weighing, say, 300 tons.
There has to be a boat or combination of boats. Then it's
necessary to work out how they actually loaded the boats.
The big problem, of course, is stability. Having no cranes,
what method did they use? We hope to show that here in Egypt
in the next few days.
Theory:
Your Q&As lead me to two suggestions and one observation:
-
The first technique refines the pivot approach. Use
rollers to move up a ramp to the height of the center of
gravity, with the lower portion extending off the end.
The outsides and end of the ramp should project forward
on each side of the base and be stone-reinforced,
leaving a clear vertical column. Attach a pivot at
center of gravity, which should be over the clear
column. Hang 'baskets' at each end of the obelisk with
rocks for counterbalancing. Gradually shift the rocks,
using ropes for control as the shifting weights do the
moving. Resulting operation looks like a balance with
the obelisk as the beam. (Depends on a strong pivot.)
-
Using the A-frame with pullers' ropes at the top and
ropes to the obelisk at the cross beam: use two or three
frames in a row to multiply the leverage, working off a
ramp significantly higher and opposite the obelisk's.
Pull, brace, shorten rope to obelisk; repeat.
-
Observation: the large projects such as a pyramid would
have done far more than binding the nation through
socialization during the period of 'draft' labor. It
would have created a national language: reinforcing a
'governmental version' over dialects from remote areas;
and bringing in minorities speaking other languages
altogether. It also would have served as a schooling
system with practical applications of writing,
calculating, and engineering techniques, which would
have increased commerce and the living standard. The
resultant prosperity would have been a magnet to
outlying peoples (such as the Israelites). The newcomers
would, in turn, contribute additional knowledge,
manpower, and demand, accelerating the growth.
Karl Veit Washington, DC
Response from Henry Woodlock, Whitby Bird & Partners:
The suggestion incorporates the principles of what we are
trying to do in this experiment. (See
'Second Chance'.) We are attempting to use the weight of the obelisk to
our advantage by pivoting it close to the center of gravity
(CG). The problem with pivoting the stone exactly about its
CG is that as soon as rotation begins, the CG is beyond the
pivot and the obelisk wants to move on its own. This is
difficult to control!
-
That's why we are placing the pivot in front of the CG
so that we can rotate it to about 60 degrees before the
obelisk wants to rotate on its own. At 60 percent the
free rotation is easier to control. To pull the butt end
of the obelisk down to get rotation, we can use two
methods. The first is by using counterweights as you
suggest. The second is to use men pulling horizontally
on vertical ropes attached to the butt end as described
by Mark Whitby in
the e-mail with Andrew Kulich below.
-
The problem with A-frames is both the strength of the
A-frame itself and also the number of people required to
pull. Many obelisks are placed in pairs, meaning that
there is no space to locate a run-off ramp beyond the
obelisk for the A-frames. This would need to be
positioned where the first obelisk is already
standing.
-
One of the biggest lessons learned from the pulling
exercise yesterday is how important organization of
labor is on an operation like this. There can be little
doubt that the workers, even those simply tasked with
pulling on ropes, would have been well drilled and very
skilled at what they were asked to do. Also, the chain
of command and communication are vital in such a tricky
operation. For example, you mention language. This is a
major factor in our experiment. The translation between
English and Arabic takes time, when decisions are often
being made in split seconds. For the raising, we are
considering using colored flags for certain key commands
to speed up the communication.
Theory:
Why not tie wood to the sides of the obelisk and divert the
Nile and float it to the place it needs to go and plop it in
the hole?
(name witheld by request)
Response from Owain Roberts:
This question has the same problem as the one about floating
it on a raft (see above). You just wouldn't be able to tie
enough wood to the obelisk to float it. It would have to be
a boat.
Theory:
The method for raising an obelisk would work the same way as
we developed for another primitive, though modern-day
monument raising in the desert, Burning Man. The technique
we employ to raise our annual one-ton, 40-foot rigid
monolithic structure on a flat plane, from horizontal to
vertical, using human power and age-old technology, is a
lever. This form of lever we call a boom.
Materials needed for proposed obelisk raising: rope, wood,
people.
With obelisk lying on ground, build a four-legged tower the
height of the obelisk, just in front of the base end. The
tower will have to be sturdy enough that the front two legs
will be able to support half the weight of the obelisk. Haul
rope, strong enough to lift over half the obelisk's weight �
or several ropes that sum equal strength—over the top
of the tower and attach to the top end of the obelisk. The
length of the rope—to be determined by how many people
are spaced along it to pull half the weight of the
obelisk—is fed in the opposite direction. Four guide
ropes are needed: one on each side to prevent sideways
swinging: one from the rear to keep from toppling forward:
and one spanning from the top end of the obelisk to the top
of the tower. With this last guide rope in place, remove the
back two legs of the tower, allowing the tower to pivot
downward as the obelisk raises.
With our boom-lever system in place, we now need only enough
people to pull the weight of less than half of the obelisk
(remember we're lifting the skinny end). The number of
people could be further reduced by using counter-weighting
and multiple booms or block-and-tackle pulleys.
Dan Miller San Francisco, CA
Response from Mark Whitby:
This is an interesting way of doing it. The problem is that
if an obelisk weighs 200 tons, you're saying you're going to
have to pull over 100 tons. Now, the first thing is that the
tower is as tall as the obelisk, so the angle up the side of
the rope you're pulling is at 45 degrees. Forty-five degrees
means you've got root 2 of the weight of the obelisk, which
is 1.3. So, the 100 tons of the obelisk is now multiplied up
to 132 tons, which is the pulling force.
Now, the way we calculate the pulling force for a person is
that, at maximum, a person can pull his own weight. At
maximum, while pulling on a rope, he inclines himself at 45
degrees, puts his weight down vertically, and pushes with
his feet. If he pushes too hard, the rope pulls them back
up, and the only thing countering that is his weight. This
is the theory we work on. So let's say that the weight of a
person is 100 weight (112 pounds), which is a slight
underestimation. There are 20 of those to the ton, so to
pull 130 tons, you need 20 times 130, which is 2,600 people.
This is why I think this method is a little bit
questionable.
Also, if you took a very tall obelisk, and the height of
that obelisk is such that the tower is pulling against it is
going to have to be of an equal height—that again has
its own issues, in that the structure you're building is an
80-foot tower made out of bits of timber. You'd have to make
it strong—yes, all is possible in this day and age,
but I'm not sure that necessarily they would have gone for
that. The way we're looking at it, we're going to reduce the
number of people down to 150, and maybe even less than that
to pull this obelisk to vertical.
Theory:
To increase the mechanical advantage of pulling ropes, skip
the pulleys. You can achieve greater advantage by anchoring
the end of two ropes and then pull the two ropes in the
middle with equal force in opposite directions perpendicular
(y-direction) to the direction you want to pull
(x-direction). The force exerted in the x direction is equal
to two times the y-direction force divided by the sine of
the angle the ropes make to the x direction. The less of an
angle you have, the greater of a force you direct in the x
direction. So a few people pulling on ropes tied to the
middle of the main pulling ropes can exert plenty of pulling
power. Think of putting a small weight in the middle of a
string, then try pulling the sting tight horizontally. No
matter how hard you pull, you can never get the sting
perfectly horizontal. The heavier the weight the harder you
have to pull.
P.S. I thing it was a combination of the levers to get it
started, Then the above with an A-frame to increase leverage
is what they used.
Andrew Kulich Rochester, Minnesota
Response from Mark Whitby:
The method described by Andrew Kulich is exactly what we're
proposing. (See
'Second Chance'.) The principle is this: We've got the obelisk with the
center of gravity slightly back from the pivot point. We
will need to apply a load on the base end to upset it. The
first pull will be the biggest one. We'll bring it down by
pulling on a frame that is fixed to the butt-end of the
obelisk and that extends out beyond the end. The frame,
which is very similar to frames they have on boats, will be
windlass-tight to begin with.
We will have four sets of ropes come down off the end of the
frame, and those will be pulled in a direction perpendicular
to the lie of the obelisk. We don't want to apply a
horizontal force to the obelisk, or we run the danger of
pulling the obelisk forward and pulling the pivot off its
bearings. So we will pull it sideways, and we will actually
get a six-to-one mechanical advantage.
We will windlass them tight—we will actually lash the
windlass to the pulling rope—and we'll have another
pair of ropes that we'll anchor down so the butt end comes
down. We'll pull those back over a block and anchor them.
Then we'll release the pair of ropes, which will allow a bit
of recovery in the obelisk's position. Hopefully it won't go
back to the beginning, otherwise we'll have gotten nowhere.
And then we'll pull again. We'll always have a long length
of rope to give us a maximum mechanical advantage.
As the system develops, and the center of gravity, which is
behind the roller, rotates upwards and comes to a point
where it's vertically over the roller, at that point the
obelisk is in balance. Any further movement will mean that
the obelisk will take over and move at its own accord. At
that point we'll have to be really careful. That angle is
why we've set the rotation point in the place we have. What
we want to do is have it as near to vertical as possible. It
is quite an interesting problem; it sets up the whole
geometry for the height of the ramp and everything. From
that point onwards, it doesn't matter how big an obelisk
you're dealing with. That's the sort of arrangement you'd
like to have, because it's all similar proportions.
Theory:
Why not use a pulley on level ground to gain a mechanical
advantage for the pullers?
Sent in by Travis
Response from Mark Lehner:
Well, we often get questions of why we don't use pulleys in
pyramid-building or obelisk-raising, and one very critical
piece of information here was given by Roger Hopkins on the
production of "Obelisk." He said a pulley is only as good as
a wheel is as good as its axle. In other words, they didn't
have iron or steel at this period, and for a pulley really
to work, you need a very strong axle. A pulley is
essentially a wheel. For wooden pulleys or various other
kinds of pulleys, it just didn't work. They probably had
something like the pulley as early as the Middle Kingdom,
several hundred years before the New Kingdom, but it was not
as powerful as it would have been had they made it out of
steel or iron.
Explore Ancient Egypt
|
Raising the Obelisk |
Meet the Team
Dispatches |
Pyramids |
E-Mail |
Resources
Classroom Resources
| Site Map |
Mysteries of the Nile Home
Editor's Picks
|
Previous Sites
|
Join Us/E-mail
|
TV/Web Schedule
About NOVA |
Teachers |
Site Map |
Shop |
Jobs |
Search |
To print
PBS Online |
NOVA Online |
WGBH
©
| Updated November 2000
|
|
|